Monday

weekly Update

Where we're at.
Right on schedule for February 1st.
Pictures soon -batteries died, but I bought more, then I changed camera and those batteries died...

On the first floor -
  • Kitchen done - needs floor cleaning and some scratch touch up
  • Small room done - probably some spots to touch up after the floor is in
  • Bathroom primed - ready to paint (tonight)
  • Hall - Painted and chair rail up. Some detail work needed.
  • Bedroom - half primed - the color is SOOOOO dark! Even under 2 coats of primer some of it looks dark
  • Front door latch repaired

What's left
  • Paint bathroom
  • Finish priming bedroom -paint it
  • Readhere bathtub surround
  • Put laminate floor in small room
  • Fix closet window. maybe throw some paint up in there.
  • Clean everything

No comments:

Post a Comment